Workplan and Deliverables

The following schematic shows the work packages of the project and the interaction between them and the users and stakeholders.

WP6 Management BalticAIMS
 

WP Schedule

The project kick-off was in Feb. 2021. The Final Review is planned to take place in Feb. 2023. Below you can find the planned timings of the WPs.

WP1 Requirements Consolidation: Feb. 2021 – May 2021 (closed, see the deliverables below)

WP2 Service Chain Specification: May 2021 – Sep. 2021 (closed, see the deliverables below)

WP3 Service Chain Implementation and Testing: Sep. 2021 – Mar. 2022

WP4 Service Delivery: Apr. 2022 – Oct. 2022 (ongoing)

WP5 Service Uptake and Utility Assessment: Jul. 2022 – Feb. 2023

Baltic Workshop during Oct 2022

WP6 Management: Feb. 2021 – Feb. 2023

The deliverable documents and other results of the project will be available through the links in the table below once approved by ESA.

Deliverable ID Title Event Delivery Date to ESA
D1.1 User Segmentation and Operational Practices Review PM1 04/2021
D1.2 User Requirements Specification (URS) PM1 04/2021
D2.1 Service Portfolio Definition PDR 09/2021
D2.2 Data and Platform Provisioning Plan PDR 09/2021
D2.3 Service Delivery Chain Specification PDR 09/2021
D3.1 Service Chain Verification Report (SVR) SRR 03/2022
D3.2 System and Service Chain Readiness Report (SRR) SRR 03/2022
D4.1 Service Operations and Service Chain Performance Report SOR 10/2022
D5.1 Service Utility Report FR 02/2023
  Final Report FR 02/2023

PM =Progress Meeting, PDR = Preliminary Design Review, SRR = System Readiness Review, SOR = Service Operations Review, FR = Final Review.

 